HomeContact UsSiteMapKOREAN
 
Home > Business Fields > Electricity&Machinary > Power Transmission
With the performance records, presently we are participating in 765kV Transmission lines projects and substation projects in Korea.

Further to this, we have completed 220kV Transmission Line Project in Sri Lanka in June 2002 which means the expansion of market to abroad on turnkey basis from designing to commissioning.

GS Neotek is carrying out the projects from fundamental planning to construction and maintenance
Areas
Overhead Transmission : 154kV, 345kV, 765kV
OPGW Substation : 154kV, 345kV, 765kV
Activity & Major Works
Year Project Client
2009 Paju Unjeong District electric line burying works (in progress)  
2008 765kv Sinanseong-Singapyeong T/L construction (Zone 1) (in progress)  
  154kv Sinyanggwang?Injae electric line construction (Zone 2) (in progress)  
2002 765kV Substation for Shingapyeong KEPCO
2002 345kV Transmission Line for Shigapyeong - Migeum KEPCO
2002 220kV T/L for Sri Lanka CEB CEB
2000 345kV Transmission Line for Youngheung KEPCO
2000 765kV Substation for Shinseosan KEPCO
1998 OPGW for Pyeongtaek - Ansung KDN
1998 Replacement of 154kV T/L for Yangdo KEPCO
1997 154kV T/L for LG Petrochemical LG Petrochemical
1996 Okgu 345kV Substation KEPCO
1996 345kV T/L for Youngkwang-Shinnamwon KEPCO
1995 345kV Kimhae Substation KEPCO
1994 345kV T/L for Shinsungnam Branch KEPCO
1993 154kV T/L for Youngseo-Kwangmyung KEPCO
1987 154kV T/L LG Electron
1986 OPGW for Deokso-Cheongpyung KEPCO